It’s time to start planning ahead…
November 10, 2022
Lead Times and how HLZAE can help!
In our industry, there has been a push to convert to electrical systems within a building. This can come in the form of additional power to allow for future apartment / tenant electrical upgrades or to reduce future potential Local Law 97 fines. As with many components associated with the construction industry, there are considerable (up to one year) lead times for the main electrical equipment and switchgear that enable these large power upgrades once ordered. Additionally, the logistics associated with the utility (Con Edison) bringing the additional power to a building can be up to or over a year in some cases.
HLZAE can assist by performing the necessary investigations, evaluations and planning reports for what your building requires, helping you plan and undertake proactive upgrades to stay ahead of both equipment delays and utility service upgrade delays.